== Charge == | == Charge == | ||
− | + | # Identify key decisions that must be made (and justified) prior to CD-1, | |
− | + | # Make progress on (or actually make) those decisions, | |
+ | # Lay out a timeline and process for making each decision, consistent with the post-decision work and internal reviews that will be needed to complete preparations for CD-1, | ||
+ | # Ensure that those timelines and processes are understood and supported by the collaboration, and that we (together) believe we can follow them. | ||
== Agenda (2 hours total) == | == Agenda (2 hours total) == |
Revision as of 19:55, 10 October 2019
Charge
- Identify key decisions that must be made (and justified) prior to CD-1,
- Make progress on (or actually make) those decisions,
- Lay out a timeline and process for making each decision, consistent with the post-decision work and internal reviews that will be needed to complete preparations for CD-1,
- Ensure that those timelines and processes are understood and supported by the collaboration, and that we (together) believe we can follow them.
Agenda (2 hours total)
- (15 min) Detector/ optical coupling state of the field. Technology update (Toki S.)
- (15 min) Update from Detector Task Force and Detector Fabrication Review (Brad B.)
- (30 min) Understanding requirement flow down - How did we come up with decadal detector configuration? (Clarence C., Vicor B, )
- (30 min) Key decision items - number of detector types, optical coupling (Kent I.)
- (15 min) R&D plan: Current state of the plan, discussion on readout “interface” issues: resources, testing (Brenna)