LBNL-2020: Detectors Readout Modules
From CMB-S4 wiki
Jump to navigationJump to searchCharge
- Organizers to consult with relevant L2s and SEs
- Present progress towards readout technology recommendation, or decision, or status thereof
- Present progress towards optical coupling technology decision, or status thereof
- Present prototype design, and fabrication and testing plan (S4 wafers tested by end of 2020)
- Summarize/update technical risks, R&D / simulation needs to retire those risks
- Define interfaces between Detectors, Readout, and Modules. (Who provides non-detector coupling wafers? Who bonds? How are fab resources allocated between squids and detectors? Etc etc)
- Plan schedule of design reviews for these subsystems needed before CD1
Agenda
Parallel session 1
- Progress towards optical coupling technology recommendation or decision
- Summary of optical assessment and comments (15-min)
- Discussion of next milestones and steps in process (15-min)
- Progress on determining detector specifications and flowdown (20-min)
- Detector fabrication prototype design, fabrication, and testing plans
- CDFG overview (15-min)
- Wafer specifications and interfaces (15-min)
- Update from fabs - SeeQC, ANL (10-min each)
- Interfaces (10-min)
- Summarize and discuss; design review schedule, R&D, development goals for August agency review and CD-1 (15-min)
Parallel session 2
- Progress towards readout technology recommendation or decision (30 or 45-min?)
- Summary of readout assessment and comments (Amy or Zeesh)
- Discussion of next milestones and steps in process (Amy or Zeesh)
- Down-select metrics
- Systems engineering and interfaces (15 or 20 min?)
- Progress on determine readout specifications and flowdown (15 or 30-min?)
- Readout-related detector testing needs (30-min) - (Adam)
- Module and readout related testing needs for detector testing
- Discuss overall landscape, and what makes sense given status of readout downselect, and what resources are available
- Summary and discussion