Difference between revisions of "LBNL-2020: DM"

From CMB-S4 wiki
Jump to navigationJump to search
Line 17: Line 17:
 
# Introduction
 
# Introduction
 
# WBS Level 3 scope, milestones, labor & risk
 
# WBS Level 3 scope, milestones, labor & risk
## 1.09.05 Data Reduction
+
** 1.09.05 Data Reduction
## 1.09.06 Transients/Sources
+
** 1.09.06 Transients/Sources
## 1.09.04 Data Synthesis
+
** 1.09.04 Data Synthesis
## 1.09.03 Software Infrastructure
+
** 1.09.03 Software Infrastructure
## 1.09.02 Data Movement
+
** 1.09.02 Data Movement
## 1.09.07 Site Hardware
+
** 1.09.07 Site Hardware
## 1.09.01 Subsystem Management
+
** 1.09.01 Subsystem Management
 
# Baseline design simulation tool
 
# Baseline design simulation tool
 
# Subsystem design review schedule
 
# Subsystem design review schedule

Revision as of 08:59, 20 March 2020

Connection Details

https://lbnl.zoom.us/j/134985614

Monitor - Julian Borrill

Scribe - Tom Crawford

Charge

  1. Define the overall scope, schedule, cost & risk of the data management subsystem for the summer review via a fully fleshed out WBS with milestones with FTE estimates.
  2. Prepare for the baseline design simulations.
  3. Plan the schedule of design reviews needed before CD1.

Agenda

  1. Introduction
  2. WBS Level 3 scope, milestones, labor & risk
    • 1.09.05 Data Reduction
    • 1.09.06 Transients/Sources
    • 1.09.04 Data Synthesis
    • 1.09.03 Software Infrastructure
    • 1.09.02 Data Movement
    • 1.09.07 Site Hardware
    • 1.09.01 Subsystem Management
  1. Baseline design simulation tool
  2. Subsystem design review schedule
  3. General discussion

Notes

Real-time notes on this google doc; please identify your notes with your initials to help with any clarifications when we transfer them to the wiki after the session.